In England, an extension at the front of a house almost always needs planning permission, because permitted development rights do not cover any extension built forward of the principal elevation, or beyond a side wall that fronts a highway. The one exception is a small porch: up to 3 square metres in ground area, no more than 3 metres high and at least 2 metres from any boundary with a highway. Anything at the front beyond those limits needs a householder planning application.

Why a front extension is not permitted development

Permitted development rights for house extensions come from Class A of Part 1, Schedule 2 of the General Permitted Development Order 2015. Condition A.1(e) says development is not permitted if the enlarged part of the house would extend beyond a wall which forms the principal elevation of the original house, or which fronts a highway and forms a side elevation of the original house.

The Planning Portal puts it more plainly: an extension cannot be built forward of the principal elevation or, where it fronts a highway, the side elevation. So unlike a rear or side extension, there is no size of front extension that fits within the Class A rules.

A few other points from the Planning Portal apply to every house:

  • The rules apply to houses only, not to flats and maisonettes.
  • Permitted development rights can be limited or removed by a planning condition or an Article 4 direction.
  • The original house means the house as it was first built, or as it stood on 1 July 1948 if it was built before that date.

What counts as the principal elevation

The GOV.UK technical guidance on householder permitted development explains how the principal elevation is identified:

  • There will only be one principal elevation on a house.
  • In most cases it is the part of the house that fronts the main highway serving the house, directly or at an angle.
  • It will usually contain the main architectural features, such as main bay windows or a porch serving the main entrance.
  • It is usually, but not always, what you would think of as the front of the house.
  • It can include more than one wall facing the same way, for example where there are large bay windows or an L-shaped frontage.

That last point catches people out. Where this applies, the guidance says the line for deciding whether an extension extends beyond a wall follows all of those walls, so if your house has large bay windows or an L-shaped front, filling in the space beside them is still forward of the principal elevation.

Corner plots and side walls facing a road

On a corner plot, the guidance says a view has to be taken on which elevation is the principal one, and there is an extra restriction where a side elevation fronts a highway. It says that if the angle between the elevation and the highway is more than 45 degrees, the elevation will not normally be treated as fronting the highway. A highway here is any public right of way, such as a public road, public footpath or bridleway, and for the purposes of the Order it also includes unadopted streets and private ways. Our guide to side extension permitted development and planning rules covers the side limits in more detail.

The porch exception

Class D of the same Order allows a porch outside any external door of a house without planning permission, as long as:

  • the ground area, measured externally, is no more than 3 square metres;
  • no part of it is more than 3 metres above ground level; and
  • no part of it is within 2 metres of any boundary between the property and a highway.

The technical guidance says heights are measured from ground level, meaning the surface of the ground immediately next to the building. Class D does not apply where the house only exists as a home because of certain change of use rights (Classes M, N, P or Q of Part 3), and the Planning Portal notes that the porch allowance applies to houses, not to flats or maisonettes, and not where a condition, Article 4 direction or other restriction removes it.

The 2 metre rule is worth checking first. If your front wall is within 2 metres of the boundary with the pavement or road, there is no room for a permitted development porch on that wall, however small.

When you need a householder planning application

Anything at the front that goes beyond the porch limits needs planning permission. That includes a front room or entrance hall extension, a porch over 3 square metres, a porch within 2 metres of the boundary with a highway, and filling in beside a bay window. The Planning Portal says that where you go beyond the permitted development limits, a householder planning application will be required, which our householder planning application guide explains step by step.

GOV.UK guidance says that once an application has been validated, the statutory time limit for the council to decide a householder application is 8 weeks, unless a longer period is agreed in writing with the applicant. The council's fee and the other costs involved are set out in our post on planning permission costs.

Get a Quick Quote

0
people filled this out in the last hour
By submitting the form you agree to our privacy policy.
Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.

What councils look at for a front extension

Every council has its own design guidance, so the starting point is your council's householder design guide. Coventry City Council's Householder Design Guide Supplementary Planning Document (2023) is a useful example of the kind of tests councils apply:

  • Amenity issues need to be considered, but the impact on the street scene and local character is the primary consideration for the design of front extensions, including porches and canopies.
  • Front extensions are generally only acceptable where the house is set well back from the street frontage in a large plot, or set back further than the prevailing building line.
  • They are generally not acceptable unless they can be designed without projecting forward of the established building line.
  • The roof profile and materials should complement the main roof of the house, and distinctive features of the house should be kept.
  • Where there is an existing bay window, a clear separation should be kept between the bay and any porch or extension, and linking bays to porches will not normally be acceptable.
  • Front extensions should not reduce parking provision.

The building line is worth checking before you commission drawings. Under guidance like Coventry's, if the houses in your street all sit on the same line, a front extension that projects forward of it is harder to justify than one on a street where houses are already staggered or set well back.

How we check a front extension or porch

Porches and front extensions are a request we see regularly. Before advising on a porch or front addition, we ask for:

  • a photo of the front of the house, taken from the street;
  • a photo of the front door and the area where the porch or extension would go;
  • a wider photo showing the front garden, the pavement and the neighbours on either side;
  • roughly how far it is from the front wall to the pavement; and
  • the title plan, if you have one, which you can get from HM Land Registry.

The distance to the pavement matters because of the 2 metre highway rule for porches. These details help us advise on whether a porch is likely to fit within permitted development or whether a householder application is needed.

Getting certainty for a porch

If your porch fits within the Class D limits, you do not need to apply for planning permission. If you want to be certain that it is lawful, for example because the measurements are close to the limits, the GOV.UK technical guidance notes that you can apply to your council for a lawful development certificate for the proposed porch.

Frequently asked questions

Do I need planning permission for a front extension?

Yes, in almost all cases. Permitted development does not allow any extension forward of the principal elevation of the original house. The only exception is a porch within the Class D limits.

Can I extend the front of my house under permitted development?

Only with a porch: no more than 3 square metres in ground area, no more than 3 metres high, and no part within 2 metres of a boundary with a highway. Flats and maisonettes do not have this right.

How big can a porch be without planning permission?

Up to 3 square metres in ground area, measured externally, and no more than 3 metres above ground level, with no part within 2 metres of the boundary with a highway, such as a road or footpath.

Can I fill in the space beside my bay window?

Not under permitted development. The technical guidance says the principal elevation can include more than one wall facing the same way, such as large bay windows, and the line for judging whether an extension extends beyond the principal elevation follows those walls. So infilling beside large bay windows needs planning permission.